VAB SAFE HAVEN RESTORE CRAWLERWAY
RUSH Job
9915
Owner
NASA - KSC
Engineer
BRPH
Contract
$2.6 Million
Duration
9 Months
Completion
:
May 2000
Features
IDIQ contract. Restore Crawlerway to the VAB High Bay 2. Construct new Orbiter Tow Way to VAB High Bay 4. Very short construction schedule with tight work area constraints.