This project entails the building of a two story 7,000 sf addition for aerobic and weight training as well as the addition of 52 parking spaces built over an underground water retention system. The interior renovations include adding new family changing rooms, renovation and expansion of the existing woman’s locker rooms, laundry facility and child development areas. Entire facility will receive a new fire suppression system as well as modifications and improvements to the interior pool area.
PROJECT STATUS MEETING Phase 4 - #03
Downtown Orlando YMCA
RUSH Construction Job No. 0820
March 18, 2010
The next meeting: March 26, 2010 at 9:00 AM
Attendees:
Nicole Micheli - YMCA Mike Lapinski – RUSH Bill Alexander – Sun Plumbing
David Zann - PDG Mark Amato - RUSH
Corrections to 2/12/10 Meeting: None
Safety: 52,258 man-hours without a lost time incident as of 3/17/10.
1. Jobsite safety meetings are held on Fridays at 12:30. This week’s meeting will be on eye protection.
2. There was an issue with the added structural steel placement that was taken care of. During the installation a temp lighting circuit was inadvertently nicked which caused an electrical concern which was handled quickly and safely.
Quality:
1. Current As-Built log entry is #100 as of 3/1710. As-Builts will be updated on a weekly basis.
2. The City has requested an engineering detail for the 6” duct that goes through the fire wall in the hallway. PDG is working on getting this taken care of.
3. No real issues with PH 4.
4. Long discussion took place concerning the existing sewer line problems and how best to confront them. Everyone walked through the facility after the meeting to get a game plan together.
5. RUSH provided CI 588 proposal concerning the PH 4 unforeseen conditions to date to the Y.
Planned Preparatory Meetings
SPEC Description DATE-TIME
None
Security: No issues
Environmental: No issues
RFI’s:
RFI NO. OPEN RFI’S SUBMIT DATE
None
OPEN SUBMITTALS:
SUB NO. OPEN SUBMITTALS SUBMIT DATE
None
Bolded Items have been in review for 30 days or more
CHANGE ITEMS:
CI NO. DATE AWARE DESCRIPTION DATE QUOTED
588 2/15/10 Men’s Entrance Credit 3/18/10
588 2/24/10 Phase 4 Structural Adds & Unforeseen 3/18/10
589 3/1/10 Existing Sewer Main Issues Compiling
YMCA / PDG Action Items:
1. None
RUSH Action Items:
1. Provide Proposal Pricing for CI 589
Project Comments:
1. Only 1 more pour left on PH 4. This should happen on Monday. RUSH to inform the Y once schedule is confirmed.
2. The remaining hallway tile installation will start on the 29th. We need to wait and let the floor topping cure to make sure that we don’t have any bonding issues prior to tile placement.
3. No other items were noted.
Schedule:
Milestones: Complete Masonry 3/26/10
Start Remaining Floor Tile 3/29/10
Complete PH 4 5/01/10
Work to be Performed this Week.
RMC Tradeworks: Pace Electric: GRG Structures:
1. Complete 1. PH 4 Rough-in 1. Complete Masonry
Sun Plumbing: Gary Munson A/C: Southern Fire:
1. PH 4 Rough 1. PH 4 Rough 1. PH 4 Rough-in
Cc:
Mark Russell – YMCA Eduardo Rabel – RUSH T. Downs – Glass Systems
Dan Ickes - YMCA William Chivers – RUSH N. Reynolds – Apex Painting
Nicole Micheli - YMCA Michael Lapinski – RUSH M. Sanchez – Star Quality
Theresa Carter - YMCA Paul Stewart- RUSH Division 10
David Zann – Powell Design Group Tracy Mascellino - RUSH All-County Insulation
Mike – Florida Drywall J. Boros – RMC
D. Huysman – Southern Fire D. Yovaish – Pace Electric
J. Guzeman – GRG B. Alexander – Sun Plumbing