ASTS Facility, MacDill AFB, Tampa, FL. – 18,160 sf facility that will have two distinct areas. Warehouse and the office area that will include administrative offices, classroom, training facilities, common areas including electrical, communication and mechanical areas.
PROJECT STATUS MEETING #05
BRAC AFRC 927th – ASTS Facility, MacDill AFB, FL
W912QR-08-C-0050
RUSH-PEAK Three JOB NO. 8804
DATE: 08/12/09
The next status meeting is set for August 19, 2009 at 10:00. The location of the meeting is at the RUSH-PEAK Three trailer located at the Tanker Gate.
Attendees:
Bruce Dyke – USACE Tony Creten – RUSH-PEAK Thomas Pridemore – WDG
Tom Overman – CWSI Robert Gandolfi – RUSH-PEAK John Craven – WDG
Darrin Wedmann – CWSI Bruce Bennett – WDG
Darrin Berends - USACE
Safety: 1,143 man-hours to date. No lost time accidents.
1. Jobsite safety meetings are held on-site on Wednesdays at 12:30. All personnel are welcome. This meeting is mandatory for all on-site workers.
2. Risk factors for this week are working around heavy equipment and lightning safety.
Quality:
1. Current As-Built log entry is # 0 as of 07/28/09.
2. New Trades starting:
a. None at this time.
Planned Three Phase Meetings
SPEC Description DATE-TIME
33 11 00 Jack & Bore for Water Main TBD
Environmental:
1. The SWPPP completed forms are available on site. Please see the Superintendent.
RFI’s:
RFI NO. OPEN RFI’S SUBMIT DATE
No Open RFI’s
OPEN SUBMITTALS:
SUB NO. OPEN SUBMITTALS SUBMIT DATE
08 91 00 – 1 Louvers 7/27/09
08 91 00 – 2 Louver Samples 7/27/09
23 64 26 – 2 Calibrated Valves and Pumps 7/23/09
23 64 26 – 3 Discharge Valve and Strainer 7/23/09
26 12 19.10 – 1 3-Phase Mounted Transformers 7/21/09
26 20 00 – 1 Panelboards 7/22/09
26 27 13.10 30 – 1 Electric Meters 7/21/09
ITEMS LISTED IN BOLD ARE OVER 30 DAYS
CHANGE ITEMS:
CI NO. DATE AWARE DESCRIPTION DATE QUOTED
515 7/10/09 FM001 Revise Civil Plates 7/30/09
516 8/5/09 FM002 Medium Voltage Cable 8/18/09
COE Action Items:
1. Perform submittal review.
RUSH / PEAK Action Items:
1. Continue processing submittals.
2. Submit breakdown for WDG portion of work for FM001 Revise Civil Plates.
3. Submit RFI regarding force main location.
Project Comments:
1. The testing for the test stone columns is set for Monday, August 17.
2. Storm and sanitary structures are scheduled to arrive this week.
3. The environmental report for import fill shall arrive at the site prior to fill being delivered.
4. Water must be used to keep the dust down while sweeping the road.
Schedule:
Milestones: Stone Col. Testing - 8/17/09
Begin Install of Stone Columns - 8/18/09
Begin Fill Import @ Bldg. Pad - 8/31/09
Work to be Completed this Week.
RUSH - PEAK:
1. Supervise construction activities.
WDG:
1. Complete removing mulch from site this week.
John Burgstiner:
1. Testing of stone columns on Monday, August 17.
2. Begin installing stone columns Tuesday, August 18.
Cc:
Jeff Agee - USACE D. Campbell – WDG Construction R. Merritt – Ashe Glass
Darrin Berends - USACE D. McFadden – John Burgstiner, Inc. C. Spero – American Roll-Up Doors
Bruce Dyke - USACE J. Paul – Cocoa Masonry J. Noll – JS Specialty Products
Tom Overman - Chugach R. Ziegler – New Energy Services, Inc. A. de Silva – United Drywall
Eric Veyon - Chugach C. Dulin – Superior Mechanical J. Abrell – Architectural Sign
Eduardo Rabel – RUSH – PEAK W. Wilson – Accurate Systems Fire P. Pauleo – Allied Door & Hardware
Paul D. Stewart – RUSH – PEAK J. Leece – Morrell Architectural J. Braddy – EM-CO Metals
Robert Gandolfi – RUSH – PEAK M. Carr – K&M’s Custom Cabinetry D. Wedmann - Chugach
William Chivers – RUSH – PEAK J. Nuce – John Nuce Acoustic Ceilings
M. Lapinski – RUSH – PEAK M. Bryant – Smith Fence
T. Madigan – RUSH – PEAK J. Schumacher – JDC Doors
T. Creten – RUSH-PEAK Shawn – Florida Coast Landscaping
James Robert – RUSH-PEAK E. Wade – B&G Painting