EOD Facility, MacDill AFB, Tampa, FL. – The new Explosive Ordnance Disposal Facility will accommodate 18 full time personnel and three Government vehicles. The facility includes spaces for administrative offices and local-state law enforcement training, conditioned storage/shops spaces and vehicle garage bays. Site improvements include paved parking, site lighting and security fencing. The 10,000 square foot building construction includes cast in place walls, hollow core pre-cast concrete roofing, and a high albedo built-up roof system.
PROJECT STATUS MEETING #09
Explosive Ordnance Disposal, MacDill AFB, FL
W91278-08-C-0054
RUSH-PEAK JV JOB NO. 8803
DATE: 08/05/09
The next status meeting is set for August 12, 2009 at 9:00 am. The meeting will be held at the on-site job trailer. Please park on the fill area next to Golf Course Street.
Attendees:
Richard Burnette – 6CES Tim Madigan – RUSH-PEAK Paul Stewart – RUSH-PEAK
Mike Lapinski – RUSH-PEAK Dennis Helton - CDI Howard Ferguson – RUSH-PEAK
Tom Overman – Chugach Darrin Wedmann - CWSI
Larry Crouse – New Energy
Safety: 2,584 man-hours to date. No lost time accidents.
1. Jobsite safety meeting is held on Monday at noon on site.
2. Risk factors for this week:
a. Excavation – PPE – Pinch points.
b. Heat Stress
c. Weather – Lightning
d. Ladder safety
e. Scaffolding
Quality:
1. Current As-Built log entry is # 2 as of 08/05/09.
2. New Trades starting:
a. Ford Plumbing
Planned Three Phase Meetings
SPEC Description DATE-TIME
None
Environmental:
1. Silt Fence Inspection
RFI’s:
RFI NO. OPEN RFI’S SUBMIT DATE
None
OPEN SUBMITTALS:
SUB NO. OPEN SUBMITTALS SUBMIT DATE
01 45 04.00 10-1.1 QCS Plan update 8-03-09
03 30 00-5 Mix Design for SOG 7-24-09
03 30 00-6 Concrete Accessories for SOG 7-24-09
03 45 33-2 Pre-cast QC and MSDS 7-08-09
08 91 00-1 Metal Wall Louvers 7-29-09
09 90 00 -1 Paints and Coatings 8-05-09
23 00 00-1&2 Inline/Exhaust Fans/Diffusers 7-29-09
26 12 00.00 40-1 Liquid Filled Transformer 7-29-09
26 20 00-1 Surge Suppressors 7-08-09
27 05 28.36-1 Cable Trays 7-13-09
31 00 00-2 Earthwork – Compaction Clarification 7-27-09
33 71 02.00 20-1 Electrical Underground 7-29-09
* Bold denotes high priority or late submittals
CHANGE ITEMS:
CI NO. DATE AWARE DESCRIPTION DATE QUOTED
Existing Communications lines
COE Action Items:
1. QA.
RUSH-PEAK Action Items:
1. QC
Project Comments:
1. The lift station inspection and draw down test was not completed last week due lack of means to measure the discharge pressure of the lift station pump. R-P is requesting assistance from the COE and Base to facilitate this measurement. The base has provided a means of measuring the pressure. R-P to request test thru the COE.
2. New Energy identified a discrepancy with the power identified for the fire pump. The pump is believed to be 208V, whereas the drawings currently show 480V. R-P to clarify.
Schedule:
Milestones: Storm Drain Complete - 07-31-09
Electrical UG - 08-10-09
CIP Walls - 09-04-09
Work to be Completed this Week.
RUSH - PEAK:
1. Quality Control
Complete Development:
1. Storm drain completion and layout for water main.
TCB Walls:
1. Tying steel and placing forms.
New Energy:
1. Rough-in underground in the slab areas.
Cc:
Justin Versluis - USACE
James Roberts – RUSH – PEAK Eduardo Rabel – RUSH – PEAK
Bruce Dyke – USACE Paul D. Stewart – RUSH – PEAK
Elais Murawski – USAF – EOD Howard Fergusun – RUSH – PEAK HFerguson@peakgc.com
Paul Hohn – USAF – EOD William Chivers – RUSH – PEAK
Nicholas Last – USAF - EOD M. Lapinski – RUSH – PEAK – mlapinski@rushinc.com
Jeffrey Agee – USACE T. Madigan – RUSH – PEAK – tmadigan@rushinc.com
Darrin Wedmann - CWIS