UPGRADE VOQ FACILITIES
RUSH Job 8913
Owner U.S. Air Force
Engineer AJT
Contract $1.6 Million
Duration 14 Months 
3 Phases
Completion 1991
Features The Visiting Officer's Quarters complex, completed by RUSH Construction, Inc. for the Air Force Space Command, consists of 30 one and two bedroom apartments in three buildings.  In addition to asbestos abatement, all interior finishes were replaced and the electrical, heating and plumbing systems upgraded.  New roofs, windows, door and an exterior insulating system modernized the exterior of the facilities.  Due to occupancy constraints, this $1.6 Million dollar project was performed in phases and completed on schedule.